Design Development Documents (Fields): May 1, 2024 - September 24, 2026
Regulatory Agencies Submission / Review: September 19, 2024 - March 17, 2025
SED Submission / Review (Fields): September 19, 2024 - January 29, 2025
Construction Documents (SED Set) (Fields): September 27, 2024 - April 11, 2025
Design Development Documents Budget Estimate (Fields): September 27, 2024 - October 28, 2024
DEP Submission / Review: January 27, 2025 - July 15, 2025
Construction Documents (Concession Stand): January 30, 2025 - August 1, 2025
Construction Documents Review / Estimate (Fields): April 14, 2025 - May 16, 2025
Bid Period / Vetting & Award (Fields): July 16, 2025 - September 10, 2025
SED Submission / Review (Concession Stand): August 1, 2025 - February 9, 2026
Procurement: September 11, 2025 - October 22, 2025
Baseball / Multipurpose Field # 1: September 25, 2025 - May 14, 2026
Bid Period / Vetting & Award (Concession / Restrooms): February 11, 2026 - April 8, 2026
Multipurpose Turf Field #2 (Including Lighting): May 14, 2026 - May 10, 2027
Basketball Court & Site Work: September 22, 2026 - May 10, 2027
Sidewalks / Plaza & Paved Access Drive: September 22, 2026 - May 10, 2027